First Baptist Church Petersburg, Petersburg Alaska
Parsonage Project: We are planning to do site prep, rough plumbing and electrical in June 2024. Then we would like to in July begin construction with the goal of having the house dry, sided, exterior painted, and roofed by the end of September. Teams then could work through out the rest of the year doing inside projects. We have a completion time line of Spring/Summer 2025, or earlier if adequate teams and finances are available.
Construction needs
- Remodeling
- New construction
- Framing
- Electrical
- Masonry
- Metal
- Painting
- Plumbing
- Roofing
- Drywall
Qualifications
Construction knowledge
Contact Information:
Lee Corrao
(907) 518-1444
leecorrao@gmail.com